Weekly Construction Update: July 17, 2020

Weekly Construction Update: July 17, 2020

Read below to find out all about our current and upcoming construction projects, and road closures.

You can view a list of all of our construction projects for the season, see our interactive road work map and check current closures at our website.

Lakewood Blvd./River Ave. intersection to close July 20 for water main work

WHAT: Intersection Closure

WHERE: Lakewood Blvd. @ River Ave.

TOWNSHIP: Holland

START DATE: Monday, July 20, 2020

ESTIMATED COMPLETION DATE: Monday, Aug. 3, 2020

PROJECT DETAILS: The intersection of Lakewood Blvd. and River Ave. in Holland Township will be closed for approximately two weeks while crews perform water main work.

This permitted project is expected to begin on Monday, July 20, and be completed by Monday, Aug. 3. Note that all dates are tentative, and work is weather-dependent.

TRAFFIC IMPACT: Traffic will be routed around on a detour that uses: James St./U.S.31/144th Ave./Lakewood Blvd.

Road Closures:

Township: Road: Segment: Work: Est. Finish:
Tallmadge Luce/Linden St. M-45-20th Ave. Bank Erosion Repair TBD
Allendale/Polkton 68th Ave. Leonard St.-M-45 Bridge Rehab July 31
Georgetown Port Sheldon St. 40th Ave. to 48th Ave. Reconstruction Oct. 23
Allendale 68th Ave. Lincoln St. to Osborn St. Cross Culvert July 21
Georgetown Rosewood St. 20th Ave. to 28th Ave. Sanitary Sewer July 22
Holland Lakewood Blvd. River Ave. Intersection Water Main Aug. 3
Zeeland 64th Ave. North of Mason St. Cross Culvert July 22

Street Resurfacing:

Township: Road: Segment: Est. Finish:
Chester Wilson St. 40th Ave. to 24th Ave. July 17
Grand Haven Lakeshore Dr. Rosy Mound Dr. to Buchanan St. Aug. 10
Georgetown 14th Ave./Port Sheldon St. 44th St. to Main St. Aug. 15
Blendon 72nd Ave. New Holland St. to Port Sheldon St. July 20
Park Lakeshore Dr. Riley St. to Lakewood Blvd. July 20
Jamestown Riley St. 32nd Ave. to 8th Ave. Aug. 15

Subdivision Street Resurfacing:

Township: Est. Finish:
Holland July 31
Grand Haven August 14

Upcoming Construction Projects:

Township: Road: Segment: Work: Est. Start:
Georgetown 48th Ave. North of Fillmore St. Cross Culvert Replacement July 27
Jamestown 40th Ave. County Line to Adams St. Gravel Road Reconstruction Late July
Jamestown Adams St. 48th Ave. to 24th Ave. Resurfacing Late July

Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.

Please note that all dates are tentative and subject to change.