144th Ave. from Lincoln St. to Rich St. to close July 27-28 for culvert replacement

WHAT: Road Closure

WHERE: 144th Ave., Lincoln St. to Rich St.

TOWNSHIP: Robinson

START DATE: Monday, July 27, 2020

ESTIMATED COMPLETION DATE: Tuesday, July 28, 2020

PROJECT DETAILS: 144th Avenue in Robinson Township will be closed between Lincoln and Rich streets July 27-28 while OCRC crews perform a cross culvert replacement project.

Note that all dates are tentative, and work is weather-dependent.

TRAFFIC IMPACT: Traffic will be routed around on a detour that uses: Rich St./128th Ave./Lincoln St.

48th Ave. from Fillmore St. to Luce St. to close July 27-30 for culvert replacement

WHAT: Road Closure

WHERE: 48th Ave., Fillmore St. to Luce St.

TOWNSHIP: Georgetown

START DATE: Monday, July 27, 2020

ESTIMATED COMPLETION DATE: Tuesday, July 30, 2020

PROJECT DETAILS: 48th Avenue in Georgetown Township will be closed between Fillmore and Luce streets July 27-30 while OCRC crews perform a cross culvert replacement project.

Note that all dates are tentative, and work is weather-dependent.

TRAFFIC IMPACT: Traffic will be routed around on a detour that uses: Fillmore St./42nd. Ave./Luce St.

Road Closures:

Township: Road: Segment: Work: Est. Finish:
Tallmadge Luce/Linden St. M-45 to 20th Ave. Bank Erosion Repair TBD
Robinson 144th Ave. Lincoln St. to Rich St. Cross Culvert July 28
Georgetown 48th Ave. North of Fillmore St. Cross Culvert July 30
Allendale/Polkton 68th Ave. Leonard St.-M-45 Bridge Rehab July 31
Holland Lakewood Blvd. River Ave. Intersection Water Main Aug. 3
Allendale 68th Ave. At Pingree St. Cross Culvert Aug. 7
Georgetown Port Sheldon St. 40th Ave. to 48th Ave. Reconstruction Oct. 23

 

Street Resurfacing:

Township:  Road: Segment: Est. Finish:
Grand Haven Lakeshore Dr. Rosy Mound Dr. to Buchanan St. Aug. 10
Georgetown 14th Ave./Port Sheldon St. 44th St. to Main St. Aug. 15
Jamestown Riley St. 32nd Ave. to 8th Ave. Aug. 15

Subdivision Street Resurfacing:

Township: Est. Finish:
Holland July 31
Grand Haven August 14

Upcoming Construction Projects:

Township:  Road: Segment: Work: Est. Start:
Jamestown 40th Ave. County Line to Adams St. Gravel Road Reconstruction Late July
Jamestown Adams St. 48th Ave. to 24th Ave. Resurfacing Late July

Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.

Please note that all dates are tentative and subject to change.